Monash Freeway - Warrigal Road to Jacksons Road

Works for the section between Warrigal Road and Jacksons Road commenced in October 2007 and were completed in August 2009.

Negri Contractors constructed this section, which involves: 

  • Constructing an additional lane in each direction. The extra lanes will be provided in the centre of the existing freeway, which means no land acquisition was required for this section.
  • Widening of the Ferntree Gully Road bridge
  • Additional pier protection at several bridges
  • Landscaping.

 The entire Monash-CityLink-West Gate upgrade project is scheduled for completion in late 2010.   

Construction

The works occurred in two main stages:

Major construction

Works will occur in the centre median area to construct the additional lane in each direction. Widening of the Ferntree Gully Road bridge will also take place. 

To ensure the safety of construction workers and road users, traffic barriers will be installed in the inner lanes to provide a safety buffer for workers. Traffic will use the resurfaced emergency shoulder as a third traffic lane.

Works will occur in sections to reduce traffic impacts. 

Line marking, asphalting and finishing works

With the new lanes now constructed, asphalting and new line marking will take place. Traffic management will be removed and the new lane in each direction open to traffic.

Landscaping works will also occur at this time.

Construction working hours

Construction hours for this worksite are Monday to Friday from 7am to 5.30pm and Saturday 7am to 3pm. Some work may occur outside these hours subject to strict approval conditions. Residents will be notified in advance of out of hours work.

Should you have any further queries about work being undertaken between Jacksons Road to Warrigal Road, please contact VicRoads on 13 11 71. 

Keeping the community informed

Project update leaflets will be provided to the community throughout the project to ensure residents and businesses are well informed of project progress and developments. Updates will also be printed in local papers. 

 

Highlighted Roadworks

Current Works on Fourth Lane Inbound

12 July 2010

CityLink is carrying out strengthening work on the elevated inbound section of the road, to cater for the projected future growth in the number and size of freight vehicles. For further details, read on.

Temporary changed traffic conditions on Hyde Street - August 6 - 14

A shuttle flow/contra flow arrangement will be in place on Hyde Street between 6.30am - 2.30pm, August 6 - 14 2010